A voltage proof test answers one question: will the insulation hold when the voltage is far higher than normal? It applies a high voltage between parts that should be insulated from each other, usually live parts and accessible metal, and checks that nothing breaks down. Standards call it different names, including electric strength, dielectric withstand and hipot, but the principle is the same.
What the Test Checks
The test looks for a failure, not a measurement. It passes if the insulation withstands the voltage for the set time without flashover or breakdown. It fails if current through the insulation rises past the tester’s trip setting. That makes it different from an insulation resistance test, which gives a number you can trend over time. The two are complementary: see insulation resistance, PI and DAR and leakage current testing.
How the Test Voltage Is Set
The product standard sets the voltage, usually from a table. The main inputs are:
- Working voltage of the circuit being tested
- Insulation type: basic, supplementary or reinforced. Reinforced and double insulation get the highest test voltage.
- Overvoltage category or installation conditions, where the standard uses them
Do not pick a voltage from experience or a rule of thumb. Use the table in the standard your product is certified to.
Duration: Type Tests vs Routine Tests
| Test | When | Typical duration | Purpose |
|---|---|---|---|
| Type test | Once, on a sample, during design approval | Often 60 s | Proves the design’s insulation is adequate |
| Routine (production) test | On every unit at end of line | Often 1–2 s, sometimes at a higher voltage | Catches assembly faults such as pinched wires or creepage errors |
The exact durations and any voltage adjustment come from the standard. Many standards also require the voltage to be raised gradually rather than switched on at full value.
AC or DC?
AC tests stress insulation the way mains voltage does, but capacitive current can cause nuisance trips on high-capacitance products. DC tests avoid that, are normally run at about 1.4 times the AC rms value (the AC peak), and need the product discharged afterwards. Some standards allow either. Our guide to hipot testing, AC vs DC covers the choice in detail.
Setting the Trip Current
The trip setting decides what counts as a failure. Set it too low and normal capacitive current trips the tester. Set it too high and a weak spot passes. Start from the value the standard gives, check it against a known-good unit, and record it in the test procedure. Some standards also set a minimum output current for the tester, so that a breakdown is actually detected.
Choosing a High Voltage Tester
- Output voltage that covers the highest test in your standards, with margin
- AC, DC or both, to match your standards
- Adjustable ramp, dwell time and trip current
- Arc detection, for catching intermittent breakdown in production
- Safety interlocks, enclosure or two-hand control, and automatic discharge
- Data logging and remote control for production lines
Need help matching a tester to your standard? Contact our Melbourne team.
Safety
Voltage proof testing uses lethal voltages. Use an interlocked test area or enclosure, keep operators out of reach of the device while voltage is applied, and discharge DC-tested items before handling. Only trained staff should run the test.
Frequently Asked Questions
Is a voltage proof test the same as a hipot test? Yes. “Hipot” is short for high potential, and it is the common name for the same withstand test.
Is a high voltage proving unit used for voltage proof testing? No. A proving unit is a portable source used to check that a high voltage detector or live-line indicator works before and after use. It does not test insulation.
Does in-service “test and tag” use a voltage proof test? In-service testing in Australia under AS/NZS 3760 normally relies on insulation resistance or leakage current measurements rather than a withstand test.